Capitol Boulevard: Israel Road to M Street Design 

March 2020 – December 2021

Project Description

This design project includes completing various stages of Plans, Specifications, and Estimates (PS&E) for five separate future construction projects that will substantially reconstruct Capitol Boulevard from Israel Road to M Street, consistent with the Capitol Boulevard Corridor Plans (CBCP).

Future construction projects will include partial reconstruction of approximately 1.2 miles of a 5-lane arterial roadway to include roundabouts, access control, lane reconfiguration, multimodal improvements, illumination, planter strips, underground conversion and public/private utility adjustment or replacement as required.

Capitol Boulevard: Israel Road to M Street DesignPDF file

Project Funding

This $1,320,000 project is partially funded by the State Pedestrian and Bicycle Program:

  • State Pedestrian and Bicycle Program Funding: $1,056,000
  • Local Funding: $264,000

Project Personnel

  • City of Tumwater Project Manager: Brandon Hicks
  • Design Firm: Undetermined

If you have any questions or concerns, please contact Brandon Hicks, City Engineer, at (360) 754-4140 or email bhicks@ci.tumwater.wa.us.